Phase E: Opportunities & Solutions

Phase E
First post-BDAT phase
4 Gaps In
B+C-Data+C-App+D
Work Packages
Core output
Draft Roadmap
Phase E produces
💡 The Big Idea

Phase E (Opportunities & Solutions) is where all four BDAT Gap Analyses converge. Phase E consolidates every gap into discrete Work Packages, defines Transition Architectures as intermediate milestones, and produces the first Draft Architecture Roadmap.

Phase E is the first phase AFTER the four architecture development phases (B, C, D). It consolidates all the work done in B, C, and D into an actionable plan.

  • ▸📥 Receives all four Gap Analyses: Business (Phase B), Data & Application (Phase C), Technology (Phase D)
  • ▸📦 Creates Work Packages — discrete, implementable chunks of work for each gap
  • ▸🏗️ Defines Transition Architectures — intermediate architecture states between Baseline and Target
  • ▸🗺️ Produces Draft Architecture Roadmap (sequence of work packages over time)
  • ▸🔗 Identifies implementation dependencies between work packages
  • ▸🔄 May involve looping back to earlier phases if gaps reveal new issues

See how CDIPD's four gap analyses consolidate into work packages, Transition Architectures, and a Draft Architecture Roadmap:

4 Gap Analyses→Work Packages→Transition Architectures→Architecture Roadmap
Step 1 — All 4 Gap Analyses feed Phase E (click to see gaps)
Step 2 — Work Packages (click for details)
Step 3 — Transition Architectures (intermediate target states)
TA-1 — Foundation
WP-1WP-2WP-6
Core backend services migrated, DB upgraded, Kubernetes cluster live. Legacy PHP still running in parallel.
TA-2 — Full Platform
WP-3WP-4WP-5
All user-facing apps live, PayFlask and VSSC deployed, legacy PHP decommissioned. Target Architecture achieved.
📋 Output: Draft Architecture Roadmap

TA-1 (Q1–Q3): WP-1 + WP-2 + WP-6 → Foundation in place.
TA-2 (Q4–Q6): WP-3 + WP-4 + WP-5 → Full Target Architecture achieved.
Phase E produces the DRAFT roadmap. Phase F finalizes it into the Implementation & Migration Plan.

⚡ Phase E Exam Rules

Phase E consolidates ALL FOUR Gap Analyses (B + C-Data + C-App + D) into work packages. Transition Architectures are intermediate states between Baseline and Target. The Architecture Roadmap is drafted here and finalized in Phase F. Phase E does NOT produce the Implementation Plan — that's Phase F.

These two concepts are frequently confused on the exam. Understanding the distinction is critical for scenario questions.

4 Gap Analyses→Work Packages→Transition Architectures→Architecture Roadmap
Step 1 — All 4 Gap Analyses feed Phase E (click to see gaps)
Step 2 — Work Packages (click for details)
Step 3 — Transition Architectures (intermediate target states)
TA-1 — Foundation
WP-1WP-2WP-6
Core backend services migrated, DB upgraded, Kubernetes cluster live. Legacy PHP still running in parallel.
TA-2 — Full Platform
WP-3WP-4WP-5
All user-facing apps live, PayFlask and VSSC deployed, legacy PHP decommissioned. Target Architecture achieved.
📋 Output: Draft Architecture Roadmap

TA-1 (Q1–Q3): WP-1 + WP-2 + WP-6 → Foundation in place.
TA-2 (Q4–Q6): WP-3 + WP-4 + WP-5 → Full Target Architecture achieved.
Phase E produces the DRAFT roadmap. Phase F finalizes it into the Implementation & Migration Plan.

⚡ Phase E Exam Rules

Phase E consolidates ALL FOUR Gap Analyses (B + C-Data + C-App + D) into work packages. Transition Architectures are intermediate states between Baseline and Target. The Architecture Roadmap is drafted here and finalized in Phase F. Phase E does NOT produce the Implementation Plan — that's Phase F.

The Architecture Roadmap is Phase E's primary output and one of TOGAF's most-tested concepts. It maps the journey from Baseline to Target over time.

  • ▸📋 Lists all Work Packages in priority/dependency order
  • ▸⏱️ Shows which work packages form each Transition Architecture
  • ▸🎯 Shows estimated timeline (not a precise project plan — that is Phase F)
  • ▸📌 Phase E = DRAFT Architecture Roadmap
  • ▸📌 Phase F = FINALIZED Implementation & Migration Plan (includes the roadmap)
  • ▸⚠️ Critical exam rule: "who produces the Architecture Roadmap?" = Phase E (draft), Phase F (finalized)